Journals →  Gornyi Zhurnal →  2015 →  #2 →  Back

DEVELOPMENT OF DEPOSITS
ArticleName Efficiency cost analysis for no-blast selective mineral extraction and overburden removal using machine groups with cutter-loaders
DOI 10.17580/gzh.2015.02.07
ArticleAuthor Shemyakin S. A., Matveev D. N., Cheban A. Yu.
ArticleAuthorData

Author 1:
Name & Surname: Shemyakin S. A.
Company: Pacific National University (Khabarovsk, Russia)
Scientific Degree: Professor, Doctor of Engineering Sciences
Contacts: e-mail: chernikova@misis.ru

 

Author 2:
Name & Surname: Matveev D. N.
Company: Pacific National University (Khabarovsk, Russia)
Work Position: Postgraduate

 

Author 3:
Name & Surname: Cheban A. Yu.
Company: Institute of Mining, Far East Branch, Russian Academy of Sciences (Khabarovsk, Russia)
Work Position: Researcher
Scientific Degree: Candidate of Engineering Sciences

Abstract

The paper presents two patented combinations of no-blast selective mining machinery proposed for open pit extraction of soft and medium-hard minerals and overburden from complex structure deposits and ore bodies (coal, phosphates, fluxing stone, peat, etc.). The authors describe flow charts of selective slice-and-stripe cutting of minerals and barren (enclosing) rocks by cutter-loaders combined with self-propelled scrapers and dump trucks (the first combination) or with self-propelled two-compartment hopper and dump trucks (the second combination). For the decision-making on continuing design and industrial trail of the equipment and technologies, the first combination was tested in Urgalsky open pit coal mine, and pre-feasibility study of the machine group efficiency was carried out based on the standard procedures for estimation of net present value (NPV), profitability index (PI) and payback period (PP). From the comparison of the conventional mining with blasting, cutter-loaders and dump trucks and the offered combinations for no-blast selective mining with cutter-loaders (in terms of Urgalsky open pit mine), the latter have shown higher efficiency, which allows continuous flow process of open pit mining, minimization of loss and dilution and elimination of dangerous and environmentally unsound blasting operations.

keywords No-blast selective mining, open pit mining, cutter-loader, predicted economic efficiency, payback period
References

1. Shchadov V. M. Otkrytaya razrabotka slozhnostrukturnykh ugolnykh mestorozhdeniy Vostochnoy Sibiri i Dalnego Vostoka (Open-cast mining of complex-structure coal deposits of Eastern Siberia and Far East). Second edition. Moscow : Moscow State Mining University, 2004. 300 p. 

2. Pankevich Yu. B., Hartman G. Opyt ekspluatatsii karernykh kombaynov Surfase Miner firmy Wirtgen na gipsovykh karerakh mira (Exploitation experience of Surface Miner (Wirtgen) at the world plaster quarries). Gornaya promyshlennost = Mining Industry. 1997. No. 1. pp. 4–9. 

3. Karlykhanov V. F., Levochkin V. F., Pankevich Yu. B., Khartman G., Dolgushin V. D. Primenenie karernogo kombayna Wirtgen 2100 SM na dobyche flyusovogo syrya (Usage of surface miner Wirtgen 2100 SM during extraction of flux raw materials). Gornaya promyshlennost = Mining Industry. 1998. No. 1. pp. 38–39.

4. S. A. Shemyakin, E. S. Kligunov. Sposob vedeniya vskryshnykh i dobychnykh rabot s primeneniem karernykh kombaynov frezernogo tipa i skreperov (Method of carrying out of open and extraction works with application of milling surface miners and skrapers). Patent RF, No. 2317415. Applied: June 15, 2006. Published: December 20, 2008. Bulletin No. 5. 

5. S. A. Shemyakin. Sposob vedeniya otkrytykh gornykh rabot s primeneniem karernykh kombaynov frezernogo tipa, samokhodnykh bunkerov i avtosamosvalov (Method of open-cast mining with application of milling surface miners, self-propelled bins and dump trucks). Patent RF, No. 2517262. Applied: May 04, 2013. Published: May 27, 2014. Bulletin No. 15. 

6. Metodicheskie ukazaniya po razrabotke smetnykh norm i rastsenok na ekspluatatsiyu stroitelnykh mashin i avtotransportnykh sredstv. MDS 81-3.99 (Methodical regulations on working out of estimated standards and rates for exploitation of construction equipment and vehicles. MDS 81-3.99). Approved by the Rosstroy Decree of December 17, 1999. No. 81. (in Russian).

7. Ekonomika predpriyatiya (Business economics). Under the editorship of O. I. Volkov. Moscow, 1997. 

8. Ilin N. N., Lukmanova N. G., Nemchin A. M. et al. Upravlenie proektami (Project management). Saint Petersburg, 1996. 610 p. 

9. Metodicheskie rekomendatsii po otsenke effektivnosti investitsionnykh proektov (Methodical recommendations on assessment of efficiency of investment projects). Moscow : Ekonomika, 2000. (in Russian).

10. Trubetskoy K. N., Potapov M. G., Vinnitskiy K. E. et al. Otkrytye gornye raboty : spravochnik (Open-cast mining : reference book). Moscow : Gornoe byuro, 1994. 590 p.

Language of full-text russian
Full content Buy